
A fully entitled 22,000 square foot site approved for fourteen attached townhomes, offered at $2,750,000 — 20.6% of projected sellout, with entitlements in hand and no discretionary approvals remaining.
| Vesting tentative tract map | Approved |
| Site plan review | Approved |
| Environmental clearance | Adopted |
| Appeal period | Expired |
| Haul route | Buyer scope |
| Building permit | Buyer scope |
Construction drawings, plan check, building permit, school fees, and utility connections remain buyer scope and are carried in the soft-cost line at 18% of hard cost. The tract map has three years remaining before extension is required. A haul route approval will be needed prior to grading.
| Plan | Count | Beds / Baths | SF Each | Total SF | Price Each | $ / SF | Plan Sellout |
|---|---|---|---|---|---|---|---|
| Plan A | 6 | 3 BR / 2.5 BA | 1,520 | 9,120 | $895,000 | $589 | $5,370,000 |
| Plan B | 6 | 3 BR / 3 BA | 1,700 | 10,200 | $965,000 | $568 | $5,790,000 |
| Plan C | 2 | 4 BR / 3.5 BA | 1,880 | 3,760 | $1,095,000 | $582 | $2,190,000 |
| Total / Weighted Avg | 14 | — | 1,649 | 23,080 | $953,571 | $578 | $13,350,000 |
Plan A carries the highest per-foot price and the lowest absolute price — the standard relationship in attached product, where the smallest plan reaches the deepest buyer pool and clears first. Plan C is priced at a discount per foot to its size because four-bedroom attached product in this submarket has a materially thinner buyer pool, and the two units are positioned to close last.
Holding a 15% margin on sellout as the developer's requirement and solving backwards for land gives the maximum supportable land price. The offering price sits just below that figure.
Hard cost is the dominant variable. A $20 per foot move — roughly 7% — swings profit by $462,000 and the margin by 3.5 points. A buyer should price this deal against their own subcontractor bids rather than the $290 assumption used here. Selling costs assume a 5% total load; a developer with an in-house sales team will underwrite lower. Every figure on this slide is invented for this sample.
| # | Address | Year Built | Beds / Baths | SF | Close Date | Close Price | $ / SF |
|---|---|---|---|---|---|---|---|
| 1 | 5420 Bakman Ave | 2024 | 3 BR / 2.5 BA | 1,580 | 03/2026 | $905,000 | $573 |
| 2 | 11240 Chandler Blvd | 2023 | 3 BR / 3 BA | 1,720 | 01/2026 | $985,000 | $573 |
| 3 | 5615 Fair Ave | 2024 | 3 BR / 2.5 BA | 1,640 | 04/2026 | $942,000 | $574 |
| 4 | 11510 Otsego St | 2025 | 4 BR / 3.5 BA | 1,850 | 02/2026 | $1,065,000 | $576 |
| 5 | 5205 Case Ave | 2023 | 3 BR / 2.5 BA | 1,490 | 05/2026 | $848,000 | $569 |
| Comparable Average | 2024 | — | 1,656 | — | $949,000 | $573 | |
| S | Alder Row — projected | 2028 | — | 1,649 | Projected | $953,571 | $578 |
The comparable set is unusually tight — a seven-dollar per foot spread across five sales — which makes the projection defensible but also caps it. We have modelled a 0.9% premium to the average on the basis of 2028 delivery against a 2023–2025 comparable set, and nothing more. A buyer underwriting meaningful price appreciation over the construction period is taking a view this document does not take. Every figure here is invented for this sample.
| # | Address | Land SF | Units | Price | $ / Unit | $ / SF |
|---|---|---|---|---|---|---|
| 1 | 6120 Vineland Ave | 18,500 | 12 | $2,280,000 | $190,000 | $123 |
| 2 | 5840 Cahuenga Blvd | 24,000 | 16 | $3,120,000 | $195,000 | $130 |
| 3 | 11820 Sherman Way | 20,000 | 12 | $2,340,000 | $195,000 | $117 |
| 4 | 5330 Klump Ave | 26,500 | 18 | $3,420,000 | $190,000 | $129 |
| Comparable Average | 22,250 | 15 | $2,790,000 | $192,500 | $125 | |
| S | Alder Row — offered | 22,000 | 14 | $2,750,000 | $196,429 | $125 |
All four comparables were entitled at the time of sale, which is the correct basis for comparison — unentitled land in this submarket trades 30–40% below these figures and carries the approval risk this site has already cleared. The subject prices 2.0% above the average per unit and exactly at the average per land foot, reflecting a slightly larger average unit size than the comparable set.
S
1
2
3
4
© OpenStreetMap contributors · © CARTO
Permit in six months, eighteen months of construction and closings, with sales released in two phases to hold pricing through the run.
The model assumes 2.0 closings per month across a seven-month sales run, consistent with the comparable projects in the closed-sale set. At that pace the fourteen units clear inside the twenty-four month schedule with a month of slack. A slower two-year market would extend the carry rather than break the deal — the sensitivity that matters here is cost, not absorption.
The budget is presented unlevered. A construction facility at 65% loan to cost would carry roughly $6.9 million with interest capitalised, and is not reflected in the 19.1% return on cost shown on slide 5 — a levered buyer will underwrite a materially higher equity return and a materially higher risk profile. Every figure in this document is invented for this sample.